FIFTH SCHEDULE.
|
| |
1. Procedure anterior to and for the purpose of an application for authority to prepare or adopt a scheme:—
|
| |
(a) Submission of plans and estimates.
|
| |
(b) Publication of notices.
|
| |
2. Procedure during, on, and after the preparation or adoption and before the approval of the scheme:—
|
| |
(a) Submission to the Local Government Board of the proposed scheme, with plans and estimates.
|
| |
(b) Notice of submission of proposed scheme to the Local Government Board.
|
| |
(c) Hearing of objections and representations by persons affected, including persons representing architectural or archæological societies or otherwise interested in the amenity of the proposed scheme.
|
| |
(d) Publication of notice of intention to approve scheme and the lodging of objections thereto.
|
| |
3. Procedure after the approval of the scheme:—
|
| |
(a) Notice to be given of approval of scheme.
|
| |
(b) Inquiries and reports as to the beginning and the progress and completion of works, and other action under the scheme.
|
| |
4. Duty, at any stage, of the local authority to publish or deposit for inspection any scheme or proposed scheme, and the plans relating thereto, and to give information to persons affected with reference to any such scheme or proposed scheme.
|
| |
5. The details to be specified in plans, including, wherever the circumstances so require, the restrictions on the number of buildings which may be erected on each acre, and the height and character of those buildings.
|